RANDALL BOULEVARD

This entire project is in the County’s Long-Range Transportation Plan. This improvement will relieve congestion and increase capacity to residents of the Estates.


PROJECT GOALS:  


  • Complete an intersection improvement at Randall Blvd. and Immokalee Rd that will relieve congestion and increase capacity 
  • Widen Randall Boulevard from Immokalee Road to 8th Street providing for future 6-lanes

  

PROJECT FEATURES:  


  • Four-lane divided roadway within a six-lane typical section 
  • Treatment and attenuation of stormwater run-off by means of ponds 
  • Maintenance of existing stormwater flow by the installation of pipes under the roadway  
  • Option features such as streetlights, on-road bike lanes, and a 12-foot pathway (pending public input)


COSTS AND FUNDING:  


  • Total project cost is estimated at $23 M 
  • Current budgeted funding in the next 5 years is approximately $16 M 
  • The current shortfall is $7 M


SCHEDULE:  


  • Estimated start FY 2019 
  • Estimated completion FY 2023